- HG/T 20519.26-1992
- in force
Standard ID:
HG/T 20519.26-1992
Standard Name:
Equipment pipe opening orientation diagram
Chinese Name:
设备管口方位图
Standard category:
Chemical industry standards (HG)
-
Date of Release:
1993-01-18 -
Date of Implementation:
1993-04-01
Standard ICS number:
General, Terminology, Standardization, Documentation>>Technical Drawing>>01.100.01 Technical Drawing General 71.010China Standard Classification Number:
>>>>G0 Engineering Construction>>Raw Materials Industry, Communications, Broadcasting Engineering>>P72 Petrochemical, Chemical Engineering
Skip to download
Summary:
HG/T 20519.26-1992 Equipment pipe opening orientation diagram HG/T20519.26-1992 standard download decompression password: www.bzxz.net
Some standard content:
Equipment pipe opening orientation diagram
HG 20519.26-92
Equipment pipe opening orientation diagram
HG20519.26-92
1 Non-standard equipment should draw a pipe opening orientation diagram, using A4 drawing sheet and simplified plane drawing. Draw a drawing for each equipment number. Equipment with the same structure but different pipe opening orientation can be drawn on the same drawing. 2 The pipe opening orientation diagram should indicate the position of the equipment's pipe opening, tank ear (hanging column), support leg (or ear seat), grounding plate, tower skirt bottom reinforcement rib and manhole on the skirt, the position and number of anchor bolt holes, and mark the pipe opening symbol (consistent with the pipe opening symbol on the equipment drawing). The anchor bolt holes on the support of horizontal equipment (including heat exchangers) must be indicated if they have different diameters or different shapes (movable end or fixed end).
3 A direction mark should be drawn in the upper right corner of the drawing. The direction indicator is in the form of a circle with a diameter of 20mm, indicating the angles of the four directions of east, west, south and north, and noting the north direction \N", such as: NbzxZ.net
The north direction "N\" of the direction indicator should be consistent with the north direction "N" of the equipment layout drawing. 4 List the pipe opening table consistent with the equipment drawing above the title bar. Note the equipment assembly drawing number on the right side of the pipe opening table. For example: "Equipment assembly drawing number ××××××." 5 The line width of the pipe opening orientation diagram shall comply with the provisions of HG20519.28-92. 6 The following two points should be added to the equipment pipe opening orientation diagram: (1) Use paint to indicate the 0° position on the skirt or body to facilitate identification of the orientation during on-site installation. (2) Indicate the orientation and installation height of the nameplate. Indicate the thickness of the insulation layer so that the nameplate is exposed outside the insulation layer. See example figure
8-436 mid-span
equipment assembly drawing number ××××
GB 9115.10-88RFPN2.5 pressure gauge port L1.2GB9115.10-88RFPN2.5
feed port
GB9115.10-88RFPN2.5 gas outlet
GB9115.10-88RFPN2.5 temperature gauge port
nominal pipe port
symbol diameter
connection form
and standard||t t||500GB9115.10-88RFPN2.5 manhole
32GB9115.10-88RFPN2.5 liquid outlet pipe nominal
or name symbol diameter
project name:
design project:
XxXx tower
· port orientation diagram (example diagram)
connection form
or name
or name
Tip: This standard content only shows part of the intercepted content of the complete standard. If you need the complete standard, please go to the top to download the complete standard document for free.
HG 20519.26-92
Equipment pipe opening orientation diagram
HG20519.26-92
1 Non-standard equipment should draw a pipe opening orientation diagram, using A4 drawing sheet and simplified plane drawing. Draw a drawing for each equipment number. Equipment with the same structure but different pipe opening orientation can be drawn on the same drawing. 2 The pipe opening orientation diagram should indicate the position of the equipment's pipe opening, tank ear (hanging column), support leg (or ear seat), grounding plate, tower skirt bottom reinforcement rib and manhole on the skirt, the position and number of anchor bolt holes, and mark the pipe opening symbol (consistent with the pipe opening symbol on the equipment drawing). The anchor bolt holes on the support of horizontal equipment (including heat exchangers) must be indicated if they have different diameters or different shapes (movable end or fixed end).
3 A direction mark should be drawn in the upper right corner of the drawing. The direction indicator is in the form of a circle with a diameter of 20mm, indicating the angles of the four directions of east, west, south and north, and noting the north direction \N", such as: NbzxZ.net
The north direction "N\" of the direction indicator should be consistent with the north direction "N" of the equipment layout drawing. 4 List the pipe opening table consistent with the equipment drawing above the title bar. Note the equipment assembly drawing number on the right side of the pipe opening table. For example: "Equipment assembly drawing number ××××××." 5 The line width of the pipe opening orientation diagram shall comply with the provisions of HG20519.28-92. 6 The following two points should be added to the equipment pipe opening orientation diagram: (1) Use paint to indicate the 0° position on the skirt or body to facilitate identification of the orientation during on-site installation. (2) Indicate the orientation and installation height of the nameplate. Indicate the thickness of the insulation layer so that the nameplate is exposed outside the insulation layer. See example figure
8-436 mid-span
equipment assembly drawing number ××××
GB 9115.10-88RFPN2.5 pressure gauge port L1.2GB9115.10-88RFPN2.5
feed port
GB9115.10-88RFPN2.5 gas outlet
GB9115.10-88RFPN2.5 temperature gauge port
nominal pipe port
symbol diameter
connection form
and standard||t t||500GB9115.10-88RFPN2.5 manhole
32GB9115.10-88RFPN2.5 liquid outlet pipe nominal
or name symbol diameter
project name:
design project:
XxXx tower
· port orientation diagram (example diagram)
connection form
or name
or name
Tip: This standard content only shows part of the intercepted content of the complete standard. If you need the complete standard, please go to the top to download the complete standard document for free.
- Recommended standards
- GB/T 50123-1999 Geotechnical test method standard
- JB/T 866-1999 Copper core paper insulated star twisted lead sleeve high frequency symmetrical communication cable
- GBZ 51-2002 Diagnostic criteria for occupational chemical skin burns
- NY/T 2494-2013 Guidelines for the conduct of tests for distinctness,uniformity and stability-Perilla
- GBJ 103-1987 General drawing drawing standard GBJ103-87
- JB/T 8650.4-1997 Machine tool cooling system auxiliary nozzle
- GB/T 5009.134-2003 Determination of gramineous chloranil residues in rice
- JB/T 2447-1992 Slotted sieve plate for coal (slotted type)
- GB/T 4606-1984 Main dimensions and installation of No. 50 traction pins for road semitrailer saddles, interchangeable dimensions
- GB/T 14643.6-1993 Determination of iron bacteria in industrial circulating cooling water MPN method
- JB/T 4315-1997 Crane electronic control equipment
- GB 9326.4-1988 Oil-paper insulated self-contained oil-filled cables and accessories connectors for AC 300 kV and below
- GB 5959.8-1989 Safety of Electric Heating Equipment Part 8 Special Requirements for Electroslag Remelting Furnaces
- QX/T 521-2019 Shipborne automatic weather station
- HG/T 2365-1992 Determination of moisture content of poly(alkylene terephthalate) pellets
Please remember: "bzxz.net" is the combination of the first letters of the Chinese pinyin of the four Chinese characters "standard download" and the international top-level domain name ".net". ©2024 Standard download websitewww.bzxz.net Mail:wymp4wang@gmail.com