标准简介

OVERVIEW

中文简介

该标准规范规定了混凝土养护的替代方法要求。它适用于项目规范中引用该标准并由建筑师或工程师指定混凝土构件及养护方法的场景。标准提供默认设置和检查清单,用于根据具体项目进行定制。

English summary

This specification provides requirements for alternative methods for curing concrete. It applies when the specification is referenced in project documents and the Architect/Engineer identifies concrete elements and selects curing methods. Default settings and checklists are provided to customize the specification for specific projects.

以上为根据文件整理的内容简介。

相关标签

标准内容预览

DOCUMENT PREVIEW
点击页码切换内容
ACI 308.1-98PDF 第 1 页 · 原页码 1

M. MANDATORY SPECIFICATION CHECKLIST

P2. If sections or parts of Standard Specification ACI 308.1 are edited into project specifications or any other document, they shall not be referred to as ACI standards, since the Standard Specification has been altered.

P3. Building codes set minimum requirements necessary to protect the public. This Standard Specification may stipulate requirements more restrictive than the minimum. Adjustments to the needs of a particular project shall be made by the Architect/Engineer by reviewing each of the items in the Specification Checklist and then including the Architect/Engineer's decision on each item as a mandatory requirement in the Project Specifications.

P4. These mandatory requirements designate the specific qualities, procedures, materials, and performance criteria for which alternatives are permitted or for which provisions were not made in the Standard Specification. Exceptions to

the Standard Specification shall be made in the Project Specifications, if required.

P5. A statement such as the following will serve to make Standard Specification ACI 308.1 a part of the Project Specifications:

Work on (Project Title) shall conform to all requirements of ACI (Standard Specification number with date suffix and title) published by the American Concrete Institute, Farmington Hills, Michigan, except as modified by the requirements of these Contract Documents.

P6. The Standard Specification Checklists identify Architect/Engineer choices and alternatives. The checklists identify the sections, parts, and articles of the Standard Specification and the action required by the Architect/Engineer.

The specification is written to allow each method of curing to be a stand-alone specification. The specifier is to determine the desired results of the curing and select the appropriate section or sections to achieve those results. Section 1 shall be included with the selected sections. The specifier is to use ACI 308-92 Standard Practice for Curing Concrete as commentary for making decisions within the checklists. The alternative methods described in each section of this Standard Specification are not necessarily equal in effectiveness, cost, effect on project schedule, or impact on other aspects of the project. To use this specification, the Architect/Engineer must not only include this document by reference in the Project Specifications, but must also review and respond to the checklists. It is imperative that the Architect/Engineer

customize this specification to meet the project requirements through the checklists. The Architect/Engineer must identify the concrete elements that are to be cured, and must choose the method to be used to cure them. Further, the Architect/Engineer must determine whether deliberate curing efforts must or may terminate after a predetermined time has elapsed, or only after particular levels of concrete properties have developed. When deliberate efforts to cure the concrete are to be terminated only when particular concrete properties have developed, the Architect/Engineer must also select the test method used to measure those properties. Checklists are provided in this document to guide the Architect/Engineer through these selection processes, and the selections must be included in the Project Specifications.

Section/Part/Article of ACI 308.1-98Notes to the Architect/Engineer
1.4The Architect/Engineer shall review the referenced standards to ensure the published dates are applicable to the specific project.
1.1.1 and 1.1.2Describe the work that is to be cured as required by this specification, or alternately, describe the work that is not to be cured in accordance with this specification. Specify the elements for which this specification does not apply.
1.1.3Deliberate curing efforts may be terminated when either a predetermined time period has elapsed, or when specific levels of concrete properties have developed in the concrete in the field or in representative samples in the laboratory. The Architect/Engineer determines which of these criteria are to be employed in Paragraphs 1.1.7.1, 1.1.7.2, and 1.1.7.3.
1.1.5.1Unless the Architect/Engineer requires otherwise in the project specifications, Section 1.1.6.1 will permit the use of any of the curing methods described in Sections 2 through 7 for unformed surfaces.
1.1.5.2Unless the Architect/Engineer requires otherwise in the project specifications, Section 1.1.6.2 requires that for formed surfaces, absorbent forms be kept wet until removal, followed by the application of any of the curing methods described in Sections 2 through 7 until duration or strength requirements are met.
1.1.5.1, 1.1.5.2, and Section 5
1
第 1 / 1 页

预览内容由文件识别整理,表格、公式及文字请以原始文件为准。

原文图片预览

PAGE IMAGES

下载标准文件

ACI 308.1-98

英语 · PDF · 6 页 · 148.5 KB

前往网盘下载 ↗
ACI 308.1-98英语 · PDF
下载文件 ↓